Question: This is all the information given Below is the bill of material for a skate board. Indented BOM Skate Board Part Description Level Planning Factor
This is all the information given
Below is the bill of material for a skate board.
| Indented BOM Skate Board | ||
| Part Description | Level | Planning Factor |
| Board | 1 | 1 |
| Wheels | 1 | 4 |
| Axles | 1 | 2 |
| Hardware kit | 1 | 1 |
| Sticker set | 1 | 1 |
The master production schedule for Skate Boards for the next 6 weeks is shown below (and the MRP planned order releases for Skate Boards have been completed for you.)
| Skate Boards - Level 0 | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | |||||
| Gross Requirements | 100 | 150 | 75 | 0 | 200 | 200 | |||||
| Projected on-hand inventory=150 | |||||||||||
| Net Requirements | |||||||||||
| Planned Order Releases | |||||||||||
| Q=100; LT=1; SS=0 | |||||||||||
Fill in the gross requirements based on the BOM and the planned order releases for Skate Boards. Next, calculate the projected on-hand inventory and the net requirements for axles. Finally, based on the order policy and lead time for axles, determine the Planned Order Releases for axles.
Answer the following questions based on the values you calculated in the table above.
What is the pattern of net requirements for the prompt above from left to right over the course of the 6 weeks?
Group of answer choices
50, 150, 0, 25, 150, 150
0, 75, 125, 25, 0, 125
0, 100, 75, 0, 175, 175
100, 250, 0, 100, 50, 50
What is the pattern of planned order releases for the prompt above from left to right over the course of the 6 weeks?
Group of answer choices
100, 100, 0, 200, 200, 0
50, 150, 0, 200, 200, 50
150, 150, 100, 25, 225, 225
150, 250, 175, 25, 400, 400