Question: The table below shows the project plan activity A B C D E F G H I J K L M N Duration (days) 1
The table below shows the project plan
| activity | A | B | C | D | E | F | G | H | I | J | K | L | M | N |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Duration (days) | 1 | 2 | 3 | 4 | 14 | 14 | 16 | 12 | 14 | 10 | 5 | 4 | 6 | 3 |
| Immediate predecessors | - | A | B | A | C | C | C | DG | DG | DG | H | I | J | EFKLM |
| 1 | 1 | 1 | 1 | 1 | 2 | 2 | 2 | 3 | 1 | 1 | 2 | 1 | 2 |
a. Calculate the minimum time in which this project can be completed and determine which activities are critical. b. Calculate the float of the non-critical activities, distinguishing between the independent and the interfering float. c. Draw a cascade chart for the project. d. Describe in detail the effect on the project if only five workers are available, each of whom can carry out any of the activities