Question: The table below gives a projects activities, its predecessor(s) and the activity cost. All times are in days. Suppose the project must be finished in
The table below gives a projects activities, its predecessor(s) and the activity cost. All times are in days. Suppose the project must be finished in 20 days. What is the lowest extra cost incurred for finishing the project in 20 days?
| Activity | Normal time | Minimum time | Crash cost ($/day) | predecessor |
| A | 10 | 8 | 50 | - |
| B | 6 | 3 | 30 | - |
| C | 2 | 2 | - | B |
| D | 4 | 2 | 40 | C |
| E | 6 | 4 | 80 | A |
| F | 8 | 5 | 100 | D,E |