Question: The table below shows the schedule for a new project for Nestl. Conduct a critical path analysis to highlight the critical path. Activity Activity Name

The table below shows the schedule for a new project for Nestlé. Conduct a critical path analysis to highlight the critical path.

Activity

Activity Name

Dependent (Predecessor)

Duration (Weeks)

A

Project Outline

-

4

B

Assign Tasks

A

2

C

Task Implementation

B

3

D

Budget Designation

-

6

E

Budget Allocation

D

2

F

Budget Implementation

E

2

G

Marketing Campaign

C, F

4

H

R&D

-

5

I

Product Development

H

4

J

Product Launch

G, I

2

Step by Step Solution

3.46 Rating (159 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

First we need to define the following terms ES Earliest Start The earliest time an activity c... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!