Question: The table below shows the tasks required to assemble a widget in your factory and the time to complete each task. Currently you have six

The table below shows the tasks required to assemble a widget in your factory and the time to complete each task. Currently you have six employees each assigned to one task.
\table[[Task,Task 1,Task 2,Task 3,Task 4,Task 5,Task 6],[\table[[Capacity],[(Units/H],[our)]],14,23,8,20,20,13]]
What is your output rate of widgets per labor hour? (calculate to two decimal places 999.99)