Question: The table below shows the tasks required to assemble a widget in your factory and the time to complete each task. Currently, you have six

The table below shows the tasks required to assemble a widget in your factory and the time to complete each task. Currently, you have six employees each assigned to one task.

Task 1 Task 2 Task 3 Task 4 Task 5 Task 6
13 Minutes 23 Minutes 20 Minutes 15 Minutes 6 Minutes 11 Minutes

What is your output rate of widgets per labor hour? (calculate to two decimal places 999.99)

The correct answer is 0.43. I am just looking for the steps to get that answer. Thanks!