Question: The table shows the data for a maintenance project. Activity Description Precedence Relationship A B D E F G H Dismantling Repair of bolster pockets

The table shows the data for a maintenance
The table shows the data for a maintenance project. Activity Description Precedence Relationship A B D E F G H Dismantling Repair of bolster pockets Repair side frame rotation stop legs Check friction blocks and all springs Repair bolster rotation stop gibs. Repair side frame column wear plates Repair bolster pivot Assemble Painting A A B E D, F, G H Time (in minutes) 35 50 85 40 27 63 220 70 52 [i] Copy and paste the following table to write your answer. [2+2+2+2 = 8] S No Path Duration Critical Path (Y/N) Project Duration