Question: The task named 'Define special logistic needs' is estimated to take 15 days. The task type is the default task type. Mark is assigned to
The task named 'Define special logistic needs' is estimated to take 15 days. The task type is the default task type. Mark is assigned to work 100% of his time for 120 hours. Change the work to 32 hours. What is the new duration?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts