Question: The tasks and immediate predecessors with three time estimates (days) are presented in tabular form. Task Immediate predecessors Optimistic Most Likely Pessimistic A None 21
- The tasks and immediate predecessors with three time estimates (days) are presented in tabular form.
| Task | Immediate predecessors | Optimistic | Most Likely | Pessimistic |
| A | None | 21 | 31 | 63 |
| B | None | 17 | 24 | 59 |
| C | A | 31 | 52 | 115 |
| D | A | 17 | 28 | 38 |
| E | C | 28 | 49 | 70 |
| F | D | 21 | 31 | 63 |
| G | B | 21 | 42 | 105 |
| H | E, F | 14 | 24 | 35 |
| I | G,H | 24 | 77 | 108 |
Using the network analysis technique, PERT (Programme Evaluation and Review Technique), draw the network diagram and find out the critical path.
(15 marks)
- List some fundamental questions that a project manager needs to ask to start the process of resource allocation.
- List three (3) tools/techniques used for Quality Control.
(7 marks)