Question: The tasks and immediate predecessors with three time estimates (days) are presented in tabular form. Task Immediate predecessors Optimistic Most Likely Pessimistic A None 21

  1. The tasks and immediate predecessors with three time estimates (days) are presented in tabular form.

Task

Immediate predecessors

Optimistic

Most Likely

Pessimistic

A

None

21

31

63

B

None

17

24

59

C

A

31

52

115

D

A

17

28

38

E

C

28

49

70

F

D

21

31

63

G

B

21

42

105

H

E, F

14

24

35

I

G,H

24

77

108

Using the network analysis technique, PERT (Programme Evaluation and Review Technique), draw the network diagram and find out the critical path.

(15 marks)

  1. List some fundamental questions that a project manager needs to ask to start the process of resource allocation.

  1. List three (3) tools/techniques used for Quality Control.

(7 marks)

(3 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!