Question: The tasks given in the following table must be performed to finish a project (all durations are in days). Draw the project network. Find
The tasks given in the following table must be performed to finish a project (all durations are in days). Draw the project network. Find the critical path. Set up the mathematical model that could be used to find the project's critical path. a. b. C. Activity A B C D E F G H T J K Immediate Predecessors A A B,C C CD_F_HG 2 EF a LO 5 4 4 5 2 1 2 - 4 4 5 Days m b 6 7 6 8 5 6 7 CO 6 3.5 5 2 3 6 3 COLO LO 5 7 10 LO 6 8 5 00 6 9
Step by Step Solution
3.42 Rating (139 Votes )
There are 3 Steps involved in it
0 Project Network TF0 OAG 066 TF0 B12 TF1 GCH 7512 FF 1 TF0 12D18 FFb TF 55 11E c Mathemat... View full answer