Question: The team is brainstorming possible risks which may occur on the project. What step are they conducting within risk management? Question 2 6 Select one:

The team is brainstorming possible risks which may occur on the project. What step are they conducting within risk management?
Question 26Select one:
a.
Risk Planning
b.
Risk Identification
c.
Risk Analysis
d.
Risk Response
e.
Risk Monitoring and Control