The technical development working group has presented to you the network diagram to show the planned...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
The technical development working group has presented to you the network diagram to show the planned sequence of activities in a workstream they will be working on. Besides the diagram, they show you a summary table of the activities, predecessors, duration in days and the number of people assigned to each activity. 1 A = 2 B = 3 C = 3 2 Activity Predecessor A B C D E F G H A B B C D, E G F, H, I 4 3 D=6 2 E=4 Duration (Days) 3 3 6 4 1 5 3 4 2 G=5 5 F = 1 2 3 H = 3 No. of People (resources) 2 3 3 2 1 1 3 7 6 J = 2 1=4 Person-days 8 a. Compute the person days planned for each activity in the table above. Provide your answer in the last column of the Table above (2 marks) b. In the following table define each project path (by listing the Activities in order), the days they will take to complete the activities on each path, and the slack on each path (8 marks) Path Activities Path 1 Path 2 Path 3 Path 4 Path 5 Path 6 A, B, C, E, G, I, J Total Duration for Path in days 20 27 18 A, B, D, E, G, I, J A, B, C, E, G, I A, B, D, E, G, I 25 A, B, C, E, H, I, J 25 32 A, B, D, E, H, I, J 0 7 2 5 5 Slack on Path in days 12 c. What is the Critical Path illustrated by the ADM network diagram? List the Activities involved and the total duration? (2 marks) d. This part of the project should be completed over thirteen (13) working-days, and six (6) people are allocated to that team. The members of the working group have asked you to explain how this can be done. Here are some key considerations: . It will be impossible to start the earlier. • The Project Sponsor has made it clear that the Go Live for the pilot node should be in 13 days and cannot be extended. . Number of People Begin your explanation by building a histogram in the following grid. Then phase the Activities and allocate the resources as required to meet the objectives. The final diagram that you provide as your answer must be clear, readily understandable, and illustrate how you can level/smooth this workstream to complete the activities in the allocated time with the available resources. Use colour shading to distinguish activities (10 marks) 9 8 7 6543 There is no funding available for additional staff or overtime. The general sequence of the activities shown in the ADM must be achieved. Fortunately, all members of the team can do any task that is required. 2 1 1 2 3 4 5 6 7 8 Project Days 9 10 11 12 13 14 15 e. Finally, briefly explain how you have achieved this objective and your reasoning behind the leveling/smoothing The technical development working group has presented to you the network diagram to show the planned sequence of activities in a workstream they will be working on. Besides the diagram, they show you a summary table of the activities, predecessors, duration in days and the number of people assigned to each activity. 1 A = 2 B = 3 C = 3 2 Activity Predecessor A B C D E F G H A B B C D, E G F, H, I 4 3 D=6 2 E=4 Duration (Days) 3 3 6 4 1 5 3 4 2 G=5 5 F = 1 2 3 H = 3 No. of People (resources) 2 3 3 2 1 1 3 7 6 J = 2 1=4 Person-days 8 a. Compute the person days planned for each activity in the table above. Provide your answer in the last column of the Table above (2 marks) b. In the following table define each project path (by listing the Activities in order), the days they will take to complete the activities on each path, and the slack on each path (8 marks) Path Activities Path 1 Path 2 Path 3 Path 4 Path 5 Path 6 A, B, C, E, G, I, J Total Duration for Path in days 20 27 18 A, B, D, E, G, I, J A, B, C, E, G, I A, B, D, E, G, I 25 A, B, C, E, H, I, J 25 32 A, B, D, E, H, I, J 0 7 2 5 5 Slack on Path in days 12 c. What is the Critical Path illustrated by the ADM network diagram? List the Activities involved and the total duration? (2 marks) d. This part of the project should be completed over thirteen (13) working-days, and six (6) people are allocated to that team. The members of the working group have asked you to explain how this can be done. Here are some key considerations: . It will be impossible to start the earlier. • The Project Sponsor has made it clear that the Go Live for the pilot node should be in 13 days and cannot be extended. . Number of People Begin your explanation by building a histogram in the following grid. Then phase the Activities and allocate the resources as required to meet the objectives. The final diagram that you provide as your answer must be clear, readily understandable, and illustrate how you can level/smooth this workstream to complete the activities in the allocated time with the available resources. Use colour shading to distinguish activities (10 marks) 9 8 7 6543 There is no funding available for additional staff or overtime. The general sequence of the activities shown in the ADM must be achieved. Fortunately, all members of the team can do any task that is required. 2 1 1 2 3 4 5 6 7 8 Project Days 9 10 11 12 13 14 15 e. Finally, briefly explain how you have achieved this objective and your reasoning behind the leveling/smoothing
Expert Answer:
Answer rating: 100% (QA)
Lets address this question step by step a Compute the person days planned for each activity in the table above Persondays are calculated as the product of the duration of the activity in days and the ... View the full answer
Related Book For
Management Accounting Information for Decision-Making and Strategy Execution
ISBN: 978-0137024971
6th Edition
Authors: Anthony A. Atkinson, Robert S. Kaplan, Ella Mae Matsumura, S. Mark Young
Posted Date:
Students also viewed these computer network questions
-
Take a look at the company Lycopodium Limited (LYL) and answer the question. Develop an understanding of the firm's business model. Some questions that you might consider are: 1. What are the main...
-
Planning is one of the most important management functions in any business. A front office managers first step in planning should involve determine the departments goals. Planning also includes...
-
Suppose that we wish to evaluate the integral 1= F(x) dx'. Use a linear mapping x'= 4x + A2 to map the region (-1,1) on the x axis to the region (A,B) on the x' axis, where B=A+Ax. (You should solve...
-
Add to Graph a method subgraph() that takes a SET as its argument and returns the induced subgraph (the graph comprising the specified vertices together with all edges from the original graph that...
-
(a) If a drop of liquid has capacitance 1.00 pF, what is its radius? (b) If another drop has radius 2.00 mm, what is its capacitance? (c) What is the charge on the smaller drop if its potential is...
-
Two plane mirrors form a 70.0° angle as shown. For what angle θ is the final ray horizontal? 70.0
-
A large electronics firm that hires many workers with disabilities wants to determine whether their disabilities affect such workers' performance. Use the level of significance \(\alpha=0.05\) to...
-
Cox Electric makes electronic components and has estimated the following for a new design of one of its products: Fixed cost = $10,000 Material cost per unit = $0.15 Labor cost per unit = $0.10...
-
Assume that a bond has an annual coupon rate of 6.80 percent, but makes coupon payments on a semi-annual basis, has a par value of $1,000, a yield to maturity of 7.20 percent, and a current price of...
-
The Fashion Rack is a retail merchandising business that sells brand-name clothing at discount prices. The firm is owned and managed by Teresa Lojay, who started the business on April 1, 20X1. This...
-
ces Knowledge Check 01 A company has the following selected account balances: Sales Sales Discounts Sales Returns and Allowances Sales Salaries Expense Store Supplies Expense Advertising Expense Cost...
-
The following information is available for the Danske Company: Denominator hours for May Actual hours worked during May standard hours allowed for May Flexible budget fixed overhead cost Actual fixed...
-
Stevens and Sons, Incorporated has 100,000 shares of $4.50 par value, 10% NON CUMULATIVE preferred outstanding and 800,000 shares of $ 50 par value common stock outstanding Both classes of stock have...
-
Ryan Seacrest was reviewing the company's activities at the end of the year (2025) and decided to prepare a retained earnings statement. At the beginning of the year, assets were $530,000,...
-
Journalize the transaction Analyze the transaction and prepare the journal entry. Paid $880 cash on amount owed on truck and $440 on amount owed on cleaning supplies. Date Account Jul 18 Debit Credit...
-
Cash Accounts Receivable Supplies Property and Equipment Other Assets Accounts Payable Notes Payable $ 5,500 115,600 32,000 235,500 14,200 37,600 185,000 Other Liabilities 25,600 Sales Revenue...
-
Youve collected the following information from your favorite financial website. 52-Week Price Stock (Div) Div Yld % PE Ratio Close Price Net Chg Hi Lo 77.40 10.43 Palm Coal .36 2.6 6 13.90 .24 56.61...
-
Solve the relation Exz:Solve therelation ne %3D
-
How can management accounting information produce behavioral and organizational reactions?
-
What is an ethical control system, and what are its key elements?
-
What does the term breakeven point mean?
-
An analysis by Professor Peter M Rothwell and his colleagues (Nuffield Department of Clinical Neuroscience, University of Oxford, UK) published in 2012 in the medical journal The Lancet...
-
The following table shows the result of the 2018 General Elections in Pakistan, along with the vote share predicted by several organizations in the days before the elections. The sample sizes were...
-
The Chinese Academy of Sciences and the Chinese Academy of Environmental Planning conducted a survey of about 563 Chinese, with a tertiary education, about their interest in reducing global warming....
Study smarter with the SolutionInn App