Question: Consider the data about project activities given in the table below (a) Schedule the work in such a way that each person always has only

Consider the data about project activities given in the table belowActivity Predecessor(s) Duration (Days) A B C D E FCH G J

(a) Schedule the work in such a way that each person always has only one task to perform (do not reduce the durations of activities or insert buffers as yet).

(b) Indicate the critical chain.

(c) Indicate where the feeding buffers should be inserted.

(d) What is the difference in the lengths of the critical path and the critical chain?

Activity Predecessor(s) Duration (Days) A B C D E FCH G J ACDE H D, J E, B F - 233232242 Resources John Sue Sue and John Sue and Al John Ann Sue Al

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related MegaProject Management Questions!