Question: The time required to complete a project is normally distributed with a mean of 8 0 weeks and a standard deviation of 1 0 weeks.

The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract puts in a due date of 80 weeks, what is the probability that they will have to pay a penalty? a.1.000 b.1/8.0.500 d. o

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!