Question: The time required to complete a project is normally distributed with a mean of 50 weeks and a standard deviation of 10 weeks. The construction
The time required to complete a project is normally distributed with a mean of 50 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract puts in a due date of 42 weeks, the probability that they will have to pay a penalty is:______________