Question: The time to assemble the first unit on a production line is 10 hours. The learning rate is 0.94. Approximately how long will it

The time to assemble the first unit on a production line is 10 hours. The learning rate is 0.94. Approximately how long will it take for the seventh unit to be assembled? The number of hours needed for the seventh unit to be assembled is hours. (Round to one decimal place.)
Step by Step Solution
There are 3 Steps involved in it
y axb where y cumulative average time per ... View full answer