Question: The total budget for a project is $ 1 , 2 5 0 , 0 0 0 . Assume that the project has an actual
The total budget for a project is $ Assume that the project has an actual cost at month of $ a scheduled cost of $ and an earned value of $
a What are the Schedule Variance and the Cost Variance?
b What are the SPI and CPI?
c What is it now estimated that the project cost will be when it is ultimately completed?
d What is it going to cost from here forward to complete the project?