Question: The total cost for a design project was $8702. The project was carried out by technicians earning $106 per day and draftsman earning $95 per
The total cost for a design project was $8702. The project was carried out by technicians earning $106 per day and draftsman earning $95 per day. If 85 man days were used on the project, how many man days were draftsman employed?