Question: The total idle time per cycle for the process = enter your response here seconds (enter your response as a whole number). The Action Toy

The total idle time per cycle for the process = enter yourThe total idle time per cycle for the process =

enter your response here

seconds (enter your response as a whole number).

The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,600 units per 40-hour workweek