Question: The total plan for the project involved 1 0 0 0 staff - days of value ( the Budgeted at Completion or BAC ) accumulated
The total plan for the project involved staffdays of value the Budgeted at Completion or BAC accumulated over months with a staff of fulltime people. At the month mark, with no open tasks, the total accumulated earned value is staffdays. The plan at this point is for staffdays to have been earned. Alas, the actual amount spent because extra staff time has already been spent on this project is staffdays.
A summary of the facts:
Original project cost: staffdays
Original project schedule: months
Planned value: staffdays at months
Actual cost: staffdays
Earned value: staffdays
Current monthly staff: people
The earned value questions that are often asked are:
What is the current cost shortfall in as measured by the Cost Variance CV
What is the current work productivity as measured by the Cost Performance Index CPI What is the current schedule shortfall in as measured by the Schedule Variance SV
What is the current schedule efficiency as measured by the Schedule Performance Index SPI
What is the projected total cost Estimate at Completion EAC
a If we assume cost variance was atypical and the rest of the project will go as originally planned
b If we assume cost variance was typical and the rest of the project will have a proportional variance
c If we assume we can replan the remaining project and make a whole new estimate?
What is the projected schedule Estimate at Completion EAC
a If we assume schedule variance was atypical and the rest of the project will be as originally planned
b If we assume schedule variance was typical and the rest of the project will have a proportional variance
c If we assume we can replan the remaining project and make a whole new estimate?
What are the remaining costtocomplete and scheduletocomplete figures for each of a b and c
What is the intensity of work required to finish the work with the available funds? These funds can be defined as either the original Budget at Completion BAC or the current Cost Estimate at Completion EAC
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
