Question: The total plan for the project involved 1 0 0 0 staff - days of value ( the Budgeted at Completion or BAC ) accumulated

The total plan for the project involved
1
0
0
0
staff
-
days of value
(
the Budgeted at Completion or BAC
)
accumulated over
1
0
months with a staff of
5
full
-
time people. At the
4
-
month mark, with no open tasks, the total accumulated earned value is
3
2
0
staff
-
days. The plan at this point is for
3
4
0
staff
-
days to have been earned. Alas, the actual amount spent
(
because extra staff time has already been spent on this project
)
is
3
7
0
staff
-
days. A summary of the facts:
*
Original project cost:
1
0
0
0
staff
-
days
*
Original project schedule:
1
0
months
*
Planned value:
3
4
0
staff
-
days at
4
months
*
Actual cost:
3
7
0
staff
-
days
*
Earned value:
3
2
0
staff
-
days
*
Current monthly staff:
5
people
6
.
What is the projected schedule Estimate at Completion
(
EAC
)
?
a
.
If we assume schedule variance was atypical
(
and the rest of the project will be as originally planned
)
?
b
.
If we assume schedule variance was typical
(
and the rest of the project will have a proportional variance
)
?
c
.
If we assume we can re
-
plan the remaining project and make a whole new estimate?
7
.
What are the remaining cost
-
to
-
complete and schedule
-
to
-
complete figures for each of a
,
b
,
and c
?
8
.
What is the intensity of work required to finish the work with the available funds?
(
These funds can be defined as either the original Budget at Completion
(
BAC
)
or the current Cost Estimate at Completion
(
EAC
)
.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!