Question: The total plan for the project involved 1 0 0 0 staff - days of value ( the Budgeted at Completion or BAC ) accumulated
The total plan for the project involved
staff
days of value
the Budgeted at Completion or BAC
accumulated over
months with a staff of
full
time people. At the
month mark, with no open tasks, the total accumulated earned value is
staff
days. The plan at this point is for
staff
days to have been earned. Alas, the actual amount spent
because extra staff time has already been spent on this project
is
staff
days. A summary of the facts:
Original project cost:
staff
days
Original project schedule:
months
Planned value:
staff
days at
months
Actual cost:
staff
days
Earned value:
staff
days
Current monthly staff:
people
What is the projected schedule Estimate at Completion
EAC
a
If we assume schedule variance was atypical
and the rest of the project will be as originally planned
b
If we assume schedule variance was typical
and the rest of the project will have a proportional variance
c
If we assume we can re
plan the remaining project and make a whole new estimate?
What are the remaining cost
to
complete and schedule
to
complete figures for each of a
b
and c
What is the intensity of work required to finish the work with the available funds?
These funds can be defined as either the original Budget at Completion
BAC
or the current Cost Estimate at Completion
EAC
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock