Question: The total program is worth $965,000,000. Specifically, you are the CAM (control account Manager) for the power system which includes the solar array subsystems as

The total program is worth $965,000,000.

Specifically, you are the CAM (control account Manager) for the power system which includes the solar array subsystems as well as the power distribution unit that provides power to the instrument payloads.

CA: Plumbing Subsystem
Number: OU812 Report Period: Mar 2022
in $000 Planned Value Earned Value Actual Cost Schedule Variance VAR % Cost Variance VAR %
Current Mo 65 45 59 ? ? ? ?
Cumulative 1060 900 960 ? ? ? ?
Budget At Complete 3400 Estimate At Complete 3600 Variance at Completion ?

Answer these questions:

-Schedule Variance of Current Mo?

-VAR % of Current Mo?

-Cost Variance of Current Mo?

-VAR %?of Current Mo

-Schedule Variance of current Cumulative?

-VAR % of current Cumulative?

-Cost Variance of current Cumulative?

-VAR %of current Cumulative ?

-Variance at Completion?

  1. Problem Report:

  1. Impact:

  1. Corrective Action:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!