Question: the Twin Pine Company allocates overhead based on a predetermined overhead rate of $9 per direct hour job S35 requires 8 tons of direct material
the Twin Pine Company allocates overhead based on a predetermined overhead rate of $9 per direct hour job S35 requires 8 tons of direct material at a cost of $600 per time and took employees who earn $21 per hour a total of 80 hours to complete what is the total cost of job is S35