Question: The valuations in an earned value management analysis:blan Multiple Choice may include revenue, profit, and costs. must consider general, selling, and administrative salaries. include only
The valuations in an earned value management analysis:blan
Multiple Choice
may include revenue, profit, and costs.
must consider general, selling, and administrative salaries.
include only direct costs.
do not include profits but must include overhead costs.
must be either profits or revenue.