Question: The valuations in an earned value management analysis:blan Multiple Choice do not include profits but must include overhead costs. must be either profits or revenue.

The valuations in an earned value management analysis:blan
Multiple Choice
do not include profits but must include overhead costs.
must be either profits or revenue.
may include revenue, profit, and costs.
include only direct costs.
must consider general, selling, and administrative salaries.