Question: The Work Breakdown Structure ( WBS ) comprises which of the following components? a . Objectives, deliverables, technical requirements, limits / exclusions . b .
The Work Breakdown Structure WBS comprises which of the following components?
a
Objectives, deliverables, technical requirements, limitsexclusions
b
Project charter, deliverables, milestones, client reviews.
c
Deliverables, subdeliverables, work packages, cost accounts.
d
Priorities, deliverables, subdeliverables, milestones.