Question: The Work Breakdown Structure ( WBS ) comprises which of the following components? a . Deliverables, sub - deliverables, work packages, cost accounts. b .

The Work Breakdown Structure (WBS) comprises which of the following components?
a.
Deliverables, sub-deliverables, work packages, cost accounts.
b.
Priorities, deliverables, sub-deliverables, milestones.
c.
Project charter, deliverables, milestones, client reviews.
d.
Objectives, deliverables, technical requirements, limits/exclusions.