Question: The work elements below describe a pipe installation process. Calculate the basic time and standard time for the following element groups: 1) dumping of

The work elements below describe a pipe installation process. Calculate the basic time and standard time for

The work elements below describe a pipe installation process. Calculate the basic time and standard time for the following element groups: 1) dumping of clean soil; 2) pipe positioning. 3) lubricaling, 4) compaction of bed; 5) compaction of backfill; 6) pipe pulling: 7) positioning of backhoe and tools preparation; 8) soil spreading. Note that these activities were not listed in order. Consider a total of 30% relaxation and contingency factors. Crew: A, B, E, F, G, H, J Equipment J: 6 CY backhoe Pipe length: 36 ft 3 ft 72 ft d 6 ft Backfill Bed 12 in

Step by Step Solution

3.40 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 Dumping of Clean Soil Basic time A B E F G H J 7 minutes Standard time 7 minutes 30 relaxation 30 contingency x 16 1632 minutes 2 Pipe Positioning B... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!