Question: The Z score table would be needed to answer 5. What is the expected time for 68, 95, and 99 percent completion limits (i.e. the

The Z score table would be needed to answer 5.

The Z score table would be needed to answer

5. What is the expected time for 68, 95, and 99 percent completion limits (i.e. the range)? 6. Calculate the numbers of days needed to obtain a 75% confidence level the project will be complete by. Activity Initial Node Final Node Optimistic Pessimistic Most Likely Time Estimate Time Estimate Time Estimate A 1 2 1 3 2 B 1 4 4 6 5 1 3 4 6 6 5 D 2. 6 2. 4 3 E 2. 4 1 3 N F 3 4 2 4 3 G 3 5 7 15 9 H 4 6 4 6 5 I 4 7 6 14 10 J 4 5 1 3 2 K 5 7 2 N 4 3 L 6 7 6 14 10

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!