Question: Their responses are shown in the following table: Activity Optimistic (days) Most Likely (days) Pessimistic (days) A 5 8 11 B 4 8 11 C

Their responses are shown in the following table:

Activity

Optimistic (days)

Most Likely (days)

Pessimistic (days)

A

5

8

11

B

4

8

11

C

5

6

7

D

2

4

6

E

4

7

10

  1. What is the expected completion time of the project?
  2. What is the probability of completing the project in 21 days?
  3. What is the probability of completing the project in 17 days?