Question: Microsoft Project Essential Training 40. Which is NOT a reason to save additional baselines in a project? Select an answer: to change the original baseline

Microsoft Project Essential Training

40. Which is NOT a reason to save additional baselines in a project?

Select an answer:

  • to change the original baseline to obtain management approval

  • to record significant changes to the project without losing original baseline values

  • to track performance trends over time

  • to save a baseline that includes changes due to approved change requests