Question: Microsoft Project Essential Training 40. Which is NOT a reason to save additional baselines in a project? Select an answer: to change the original baseline
Microsoft Project Essential Training
40. Which is NOT a reason to save additional baselines in a project?
Select an answer:
-
to change the original baseline to obtain management approval
-
to record significant changes to the project without losing original baseline values
-
to track performance trends over time
-
to save a baseline that includes changes due to approved change requests