Question: then the project should be accepted. A basic rule in capital budgeting is that if a project's NPV exceeds its IRR O True False Previous
then the project should be accepted. A basic rule in capital budgeting is that if a project's NPV exceeds its IRR O True False Previous No new data to save. Last checked at 9:03am DOLL Fs
Step by Step Solution