Question: There are 2 paths on a project that we are most concerned about; we know one of them is critical. One path, ABCEFG has a
There are 2 paths on a project that we are most concerned about; we know one of them is critical. One path, ABCEFG has a 75% probability of completion within the specified time frame. The other path ADEGH has a 70% probability of completion. Which of these is the critical path?
| ABCEFG | ||
| None of these are correct | ||
| ADEGH |