Question: There are 3 activities A , B , and C and those that require time to complete are 1 0 , 6 , and 5

There are 3 activities A, B, and C and those that require time to complete are 10,6, and 5, and weeks respectively. A and C are independent and you can process those in parallel. B depends on A. What will be the earliest completion time for those activities?