Question: There are 3 activities A , B , and C and those that require time to complete are 1 0 , 6 , and 5
There are activities A B and C and those that require time to complete are and and weeks respectively. A and C are independent and you can process those in parallel. B depends on A What will be the earliest completion time for those activities?