Question: There are 4 Mass Production Models M 1 , M 2 , M 3 , and M 4 taking 3 , 5 , 2 ,
There are Mass Production Models M M M and M taking and
hours of manufacturing time, respectively and their respective due dates to
the distributor are and Which priority rule from SPT FCFS CR and
EDD you would use while sequencing and why? Also, compute the
Average Job Completion Time, Average Utilization Factor, and
Average Job Lateness Duration for each of the priority rule