Question: There are different options to accelerate the project completion when resources are constrained or non-constrained. Which following option is for a non-constrained resource scenario? Select

There are different options to accelerate the project completion when resources are constrained or non-constrained. Which following option is for a non-constrained resource scenario?

Select one:

A. Establish a core project team

B. Fast-tracking

C. Compromise quality

D. Reduce project scope

E. None of the options