Question: There are different options to accelerate the project completion when resources are constrained or non-constrained. Which following option is for a constrained resource scenario? Select
There are different options to accelerate the project completion when resources are constrained or non-constrained. Which following option is for a constrained resource scenario?
Select one:
A. Establish a core project team
B. Scheduling overtime
C. Compromise quality
D. Do it twice
E. Outsourcing project work
In the cost-duration graph, we usually choose the optimal duration when
Select one:
a. the indirect costs are the highest.
b. the direct costs equal to indirect costs.
c. the direct costs are the lowest.
d. the total project costs are the lowest.
e. the total project costs are the highest.