Question: There are five activities on a project's critical path and they have standard deviations of 1, 1, 1, 3, 3 days. The standard deviation (in

There are five activities on a project's critical

There are five activities on a project's critical path and they have standard deviations of 1, 1, 1, 3, 3 days. The standard deviation (in days) of the critical path is: O A. 10.6 O B. 4.6 O C.9.8 O D. 10.2 O E. 7.8 OF. 8.8