Question: There are five activities on a project's critical path and they have standard deviations of 1, 1, 3, 5, 5 days. The standard deviation (in

There are five activities on a project's critical
There are five activities on a project's critical path and they have standard deviations of 1, 1, 3, 5, 5 days. The standard deviation (in days) of the critical path is: A. 10.6 OB. 7.8 0.9.8 D. 10.2 E. 8.8 F. 4.6