Question: There are five process groups represented in a project. Arrange them in the right order: Initiation, Design, Development. Execution, Contral Initiation, Eresution, Control, Planning, Testing
There are five process groups represented in a project. Arrange them in the right order:
Initiation, Design, Development.
Execution, Contral
Initiation, Eresution, Control, Planning, Testing
Initiation, Planning, Execution, Monitoring and Control, Clasing
Design, Development, Testing. Prototyping, Closing