Question: There are four stations in a process: Station-1, Station-2, Station-3, and Station-4. They process a single product. The flow of the accepted and rejected products
There are four stations in a process: Station-1, Station-2, Station-3, and Station-4. They process a single product. The flow of the accepted and rejected products are shown in the process flow chart.
The total volume of production is 116 products per hour. 23% of the products of Station-1 need repair and are directed to Station-3 for repair, the rest are sent to Station-2. 18% of the products of Station-2 need repair and are directed to Station-3 for repair, the rest are sent to Station-4. 12% of the incoming products of Station-3 are rejected, are sold at a low price, and leave the process. The rest go to Station-4. All the products of Station-4 are good, no need to repair, and no rejection. On average there are 3, 8, 34, and 9 products in Stations 1, 2, 3, 4, respectively.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts