Question: There are several tasks that a project customer ( or sponsor acting in that capacity ) can do to enhance the probability of success. The
There are several tasks that a project customer or sponsor acting in that capacity can do to enhance the probability of success. The task of conducting the Kickoff Meeting is generally performed independent of the project contractor who will perform the work. this statement is
Group of answer choices
FALSE. Should be prioritizing project activities
FALSE. Should be developing clear requirements
TRUE.
FALSE. Should be writing and signing the project charter