Question: There are several tasks that a project customer ( or sponsor acting in that capacity ) can do to enhance the probability of success. The

There are several tasks that a project customer (or sponsor acting in that capacity) can do to enhance the probability of success. The task of conducting the Kick-off Meeting is generally performed independent of the project contractor who will perform the work. this statement is _____________.
Group of answer choices
FALSE. Should be prioritizing project activities
FALSE. Should be developing clear requirements
TRUE.
FALSE. Should be writing and signing the project charter