Question: There are three main tasks in a project. Task A must be delivered two weeks before task C starts, and task C will start once
There are three main tasks in a project. Task A must be delivered two weeks before task C starts, and task C will start once task B is finished. What is the relationship between tasks A and B?
a. Start to Finish (SF)
b. Start to Start (SS)
c. Finish to Start (FS)
d. Finish to Finish (FF)