Question: There are three main tasks in a project. Task A must be delivered two weeks before task C starts, and task C will start once

There are three main tasks in a project. Task A must be delivered two weeks before task C starts, and task C will start once task B is finished. What is the relationship between tasks A and B?

a. Start to Finish (SF)

b. Start to Start (SS)

c. Finish to Start (FS)

d. Finish to Finish (FF)