Question: There are two major projects in progress in your organization: Project A - Software Development (this is an s-shaped project) and Project B - Annual
There are two major projects in progress in your organization: Project A - Software Development (this is an s-shaped project) and Project B - Annual tradeshow (this is a j-shaped project). You are managing a super important project C that requires an immediate input of a resource being used by both projects A and B but is otherwise unavailable. From which (or both or neither) do you borrow the resource? Why? Hint: S-Shaped curve: They start slowly, develop momentum, and then finish slowly J-Shaped curve: They start slowly , proceed slowly, and then finish rapidly