Question: There are two projects expected to be in use for 12 years and must select which is a better option. Project A is anticipated to
There are two projects expected to be in use for 12 years and must select which is a better option. Project A is anticipated to last 12 years, but is expensive and require maintenance. Project B is cheaper and require little maintenance, but must be replaced every 4 years. The salvage value of each is roughly equal to the cost of removal. Estimate the present worth of the alternatives at 3% annual interest and recommend the best option for the 12-year life. Show your work in Excel.
| Projects | A | B |
| Initial cost | $160000 | $40,000 |
| Annual O&M cost | $4320 | $540 |
| Salvage value | $0 | $0 |
| Life (years) | 12 | 4 |
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it