Question: There are two steps in a process. Two workers are in step 1, and one is in step 2. Each worker in Step 1 spends
There are two steps in a process. Two workers are in step 1, and one is in step 2. Each worker in Step 1 spends 10 minutes serving a customer, and it takes 6 minutes for the worker in Step 2 to serve a customer. The utilization of workers in Step 1 is 75%. What is the utilization of the worker in Step 2? curpe 90%