Question: There has been several changes in your project and this affected your cost and schedule estimates. This has invalidated the original estimating assumptions. What is

There has been several changes in your project

There has been several changes in your project and this affected your cost and schedule estimates. This has invalidated the original estimating assumptions. What is the estimate at completion (EAC) for your project? For calculation pick values from the following data EV = Rs. 180,000 BAC = Rs. 150,000 BCWP = Rs. 245,000 AC = Rs. 120,000 ACWP = Rs. 450,000 (select the most appropriate answer) a. Rs. 300,000 b. Rs. 325.000 c. Rs. 275,510 d. Rs. 360.000