Question: There is a project, which is planned for a 6 - month duration with $ 9 8 , 0 0 0 budget. Using the following

There is a project, which is planned for a 6-month duration with $98,000 budget. Using the
following data, calculate the planned and actual monthly budgets through the end of June.
Activity Jan Feb Mar Apr May Jun Plan % C Value
Staffing 851380%
Blueprinting 36960%
Prototype
Development 281050%
Full Design 3851610%
Construction 220220%
Transfer 10100%
\Sigma =80
Monthly Plan 8101431035
Cumulative
Monthly Actual 1015614
Cumul. Actual
At the end of April, the project manager wants to evaluate this projects progress. Please find
followings.
Schedule Variances
Planned Value of Work Scheduled (PV)
Earned Value (EV)
Schedule Performance Index (SPI)
Estimated Time to Completion
Cost Variances
Actual Cost of Work Performed (AC)
Earned Value (EV)
Cost Performance Index (CPI)
Estimated Cost to Completion
How do you like this projects progress? Please make comments based on your analysis.
 There is a project, which is planned for a 6-month duration

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!