Question: There is a project, which is planned for a 6 - month duration with $ 9 8 , 0 0 0 budget. Using the following

There is a project, which is planned for a 6-month duration with $98,000 budget. Using the following data, calculate the planned and actual monthly budgets through the end of June.
\table[[Activity,Jan,Feb,Mar,Axt,Max,Iun,Plan.,%c,Velues],[Staffing,8,5,,,,,13,80%,],[Blueprinting,,3,6,,,,9,60%,],[\table[[Prototype],[Development]],,2,8,,,,10,50%,],[Full Design,,,,3,8,?bar(5),16,10%,],[Construction,,,,,2,20,22,0%,],[Transfer,,,,,,10,10,0%,],[=,,,,,,,80,,]]
\table[[Monthly Plan,8,10,14,3,10,35],[Cumulative,,,,,,],[Monthly Actual,10,15,6,14,,],[Cumul, Actual,,,,,,]]
At the end of Anril, the project manager wants to evaluate this project's progress. Please find followings.
Schedule Variances
Planned Value of Work Scheduled (PV)
Earned Value (EV)
Schedule Performance Index (SPI)
Estimated Time to Completion
Cost Variances
Actual Cost of Work Performed (AC)
Earned Value (EV)
Cost Performance Index (CPI)
Estimated Cost to Completion
How do you like this project's progress? Please make comments based on your analysis.
 There is a project, which is planned for a 6-month duration

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!