Question: These 6 workers begin their workday at 8 : 0 0 am and work steadily until 4 : 0 0 pm . ( They are

These 6 workers begin their workday at 8:00 am and work steadily until 4:00 pm.(They are replaced with other workers for breaks and lunches, but the production is not slowed or stopped during these times.) At 4:00, no new watch parts are introduced into Station A, and the conveyor belt continues until all of the work in process inventory has been processed and leaves Station F. Thus, each morning the workers begin with an empty system. what is the capacity of the process in watches per hour? What is the labor utilization of the worker at Station F assuming the process is running at steady state?